During the year
2013-14 the Railways have completed 1,532 km of New Line, Doubling and Gauge
Conversion against a revised target of 1,525 km. Sections commissioned in 2013-14 include:
New Lines
Karur – Salem (85 Km)
Koderma – Nawadih (34 Km)
Lalitpur – Tikamgarh
(51.5 Km)
New Morinda to
Sanewal (54 Km) thereby complete commissioning of Chandigarh – Ludhiana
Qazigund – Banihal
(19 Km)
Kadur – Chikmaglur (46 Km)
Gauge Conversion:
Hanumangarh –
Sriganganagar (64 Km)
Manamadurai –
Virudunagar (67 Km)
Darum Madhepura – Murliganj (22 Km)
Kolar – Chickballapur
(85 Km)
Rangiya – Rangapara
North – Dekargaon (145 Km)
Doubling:
Panskura – Shyamchak (27 km) 3rd Line
Muri – Tulin (1.5 km) Doubling 2nd Bridge over
River Subernarekha
Jirat – Ambika Kalna
(20.23 km)
Magrahat – Diamond
Harbour (15 km)
Kursela-Karagola (17 km)
Katereah-Kosi cabin (4 km)
Madur – Mandya (19
km)
Birur – Ajjampur
(18 km)