Estimate of how much time various approval taken in India
Details
|
Time take
|
Conversion of Land use
|
7 to 12 Months
|
Project Letter of intent and License
|
3 to 6 Months
|
Pre - Construction Approvals from State level bodies
|
4 to 7 Months
|
Approvals for Construction plan Sanction
|
4 to 7 Months
|
Approvals for commencement of Construction
|
2 to 3 Months
|
Construction Period
|
22 -32 Months
|
Inspection and Approval Procedure for Building completion
|
2 - 3 Months
|
Occupancy Certification (Completion)
|
2 to 3 Months
|