State Commission's Recent Judgment..!
Mr. Jehangir Gai,
Consumer Activist
Apartment buyers are
often put in a tight spot by developers / promoters who demand more money after
initial payments
Real estate
developers who sell apartments during recession sometimes try to extract money
later, at the time of possession, or try to illegally end the agreement with
buyers on some pretext, so that the same flat can be re-sold at a higher price.
In a recent judgment, the Maharashtra State Commission has come down heavily on
one such builder.
Me. Ameet Arjundas
Israni and his wife, Ms. Meenal, had booked a flat with Bhumiraj Constructions
in an under-construction building in Navi Mumbai. The cost of the 1,249 square
feet terrace flat was Rs. 34.65 lakh. The agreement was stamped &
registered for Rs. 1.79 lakh. Parking space was sold for Rs. 1 lakh.
After the buyer paid
a substantial amount, the builder demanded interest for stage-wise construction
for areas constructed. The Mr and Ms Isranis refused to pay, as the agreement
was prospective in nature and did not provide for retrospective interest prior
to its execution.
The builder
terminated the deal for this but still sent a demand letter for the subsequent
instalments & accepted payment.
The Isranis paid 97% per cent of the agreed amount, and only
3% was left. It was payable during handing over of the flat. Construction of
the building was completed but the builder refused to give possession, claiming
the agreement had been terminated.
The Mr and Ms.
Isranis filed a consumer complaint on February 3, 2006, seeking possession of
the flat & compensation for delay.
During the pendency
of the case, the state commission granted an interim injunction restraining the
builder from creating any 3rd party interest in the flat.
The builder filed a
suit before the civil judge in Thane on April 18, 2006, for a direction that
the agreement had been validly terminated.
The court dismissed
the suit, saying the builder had not been able to prove the Mr.and Ms.Isranis
had delayed payments & so the builder did not have the right to demand Rs.
2,50,177 as interest.
The court concluded
the builder’s demand was against the terms of the agreement, and the deal
termination was illegal.
The builder defended
the consumer court case by claiming the deal was validly terminated. The
builder contended an appeal had been filed against the civil court’s judgment
and so it ought to be disregarded, though no order had been passed in appeal.
In the judgment dated
October 11, 2012, the Maharashtra state commission observed that even though
the agreement specified a schedule for payment, it was silent on if it would be
retrospectively applicable to an agreement executed after the construction was
underway.
Also, there was no
clause in the agreement providing for delay in payments due prior to execution
of the agreement. The Maharashtra state commission noted the payments were made
on time after execution of the agreement.
Accordingly, the
state commission held the termination of the agreement was illegal, and
constituted a deficiency in service.
Should Be
Compensated..!
The commission said
the Mr. and Ms.Isranis should be compensated for being deprived of a shelter
for over 6 years, despite having paid 97% of the agreed consideration.
The panel directed
Bhumiraj Construction & its partners to accept the balance 3 per cent
consideration of Rs. 1,03,950 and hand over vacant possession of the flat
without demanding delayed payment interest.
The order was to be
complied within 2 months of receipt of the balance amount.
The builder
& its partners were also held liable
to pay Rs. 5 lakh as compensation for the mental harassment and agony caused.
The amount would attract an interest of 12% a year if the amount was not paid
within 2 months.
The author is a
consumer activist
No comments:
Post a Comment